20 MW MAIBARARA GEOTHERMAL POWER PROJECT

November 5, 2014



MGI’s 20 MW Maibarara Geothermal Power Project is the first geothermal facility completed under President B.S. Aquino’s term, the first to be put on-line among the service contracts awarded by DOE in 2010, and the newest geothermal power facility in the country since 2007.

Following DOE’s confirmation of commerciality in 2008, MGI proceeded with the rapid construction of the integrated power complex, followed by testing and commissioning activities. On February 8, 2014, MGPP went into commercial operations, supplying additional 20 MW to the Luzon grid.